Step 1/5
Concept Design
This first stage of design is used to establish and prioritize project needs and goals and to discover the inherent constraints (physical, financial, schedule, etc.) of the project. During this phase we will also work collaboratively to create your project’s look and feel.
Meetings
Concept Meeting
July 7, 2018
Concept Board Meeting
July 17, 2017
Initial Concept and Pricing
July 22, 2018
100% Concept Presentation
August 13, 2018
Download Concept Presentation
Download Contractor Version (No Prices)
Concept Board
Concept Design Information
Project Goals
Create a more spacious bathroom
Install a more comfortable toilet
Consider changing to a pedestal or floating sink to create a sense of spaciousness
Consider 1. Upgrading tub/shower or 2. Repair chip in existing tub/shower or 3. Changing to a shower only
UPDATE 07/17/18: Consider shower only option
UPDATE 07/17/18: Add in a shower bench
Consider new wall and floor tile
Add storage (Note: Open shelving is OK unless under sink, in which case closed cabinets are preferred)
Upgrade lighting
Upgrade exhaust fan
Budget
$10,000
Schedule
Project Start - July 2018
Construction Completion - December 2018