Step 1/5
Concept Design

This first stage of design is used to establish and prioritize project needs and goals and to discover the inherent constraints (physical, financial, schedule, etc.) of the project. During this phase we will also work collaboratively to create your project’s look and feel.

Meetings

Concept Meeting
July 7, 2018

Concept Board Meeting
July 17, 2017

Initial Concept and Pricing
July 22, 2018

100% Concept Presentation
August 13, 2018
Download Concept Presentation 
Download Contractor Version (No Prices)

Concept Board


Concept Design Information

Project Goals

  • Create a more spacious bathroom

  • Install a more comfortable toilet

  • Consider changing to a pedestal or floating sink to create a sense of spaciousness

  • Consider 1. Upgrading tub/shower or 2. Repair chip in existing tub/shower or 3. Changing to a shower only

  • UPDATE 07/17/18: Consider shower only option

  • UPDATE 07/17/18: Add in a shower bench

  • Consider new wall and floor tile

  • Add storage (Note: Open shelving is OK unless under sink, in which case closed cabinets are preferred)

  • Upgrade lighting

  • Upgrade exhaust fan

See Bathroom Checklist

 

Budget

$10,000

 

Schedule

Project Start - July 2018
Construction Completion - December 2018